Upgrade of the pre-treatment system and associated works at the Hamilton Water Reclamation Plant
Client: Wannon Water Completed: Jan 2009
Works Completed:
Construction of a new pre-treatment filtration building including:
Relocation and installation of the existing pre-treatment disc filter
Installation of two (2 No) new pre-treatment disc filters (to be supplied by others)
Supply, installation and commissioning of the Pre-treatment Feed Pumps
Supply, installation and commissioning of the Pre-treatment Backwash Pumps
Pipework to the new Raw Water Tank, pre-treatment filter feed and discharge pipework, pre-treatment filter backwash supply and discharge pipework, and flocculation pipework rack
Supply and installation of an inline static mixer
Installation and modification of existing electrical, instrumentation and control systems including